淡江大學機構典藏:Item 987654321/94115
English  |  正體中文  |  简体中文  |  Items with full text/Total items : 62822/95882 (66%)
Visitors : 4028296      Online Users : 575
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library & TKU Library IR team.
Scope Tips:
  • please add "double quotation mark" for query phrases to get precise results
  • please goto advance search for comprehansive author search
  • Adv. Search
    HomeLoginUploadHelpAboutAdminister Goto mobile version
    Please use this identifier to cite or link to this item: https://tkuir.lib.tku.edu.tw/dspace/handle/987654321/94115


    Title: 前置時間對供應鏈管理績效之影響
    Other Titles: Impact of lead time on the performance of supply chain management
    Authors: 張淑琴;Chang, Su-Ching
    Contributors: 淡江大學企業管理學系碩士在職專班
    王居卿;Wang, Chu-Ching
    Keywords: 前置時間;供應鏈管理;限制理論;績效;lead time;Supply chain management;Theory of Constraints;Performance
    Date: 2013
    Issue Date: 2014-01-23 14:02:43 (UTC+8)
    Abstract: 本研究應用Goldratt 博士所提出的「限制理論」之管理思維與方法去改善供應鏈管理中的各個前置時間,進而提升供應鏈的管理績效。本研究將前置時間分為五項類別,分別為採購前置時間、生產前置時間、運輸前置時間、配銷前置時間及因應天候風險的前置時間;並應用限制理論的思考邏輯提出解決手法(如中央倉庫、提前下單、八大物流管制點及合理的安庫等方法);最後探討改善前置時間對提升供應鏈管理績效之影響。
    供應鏈管理的主要目標為降低成本、降低庫存及縮短交期以提升對顧客的服務,進而提升企業的競爭能力。本研究以改善前置時間為主要變數,以個案分析去探討其與訂單履行週期時間、訂單履行率和存貨周轉次數的關聯性。經實證分析及討論後,有以下重要發現:
    1. 在採購賣方導向市場下,找出長交期零件以「提前下單」改善採購前置時間,可提升訂單履行週期時間。
    2. 在客戶預測不確定及天候風險影響下,以「增加安全庫存周轉天數」及「增設八大物流管控點」的管理去提升訂單履行率。
    3. 運用「增加補貨頻率」、「縮小生產批量」及「中央倉庫」管控庫存,可提升存貨周轉次數。
    This study adopted the " theory of constraints " to improve the lead time in the supply chain management, then, to enhance the performance of supply chain management through the improvement of the lead time . In this research, the lead time is divided into five categories; namely, procurement lead time, production lead time, transportation lead time, distribution lead time and the lead time in response to weather risk. Then, this research adopted the logical thinking and methods from the " theory of constraints " to propose some solutions such as central warehouse, purchase in advance, logistics control points, safety stock and so on. Finally, the research was certified to enhance the performance of the supply chain management by improving lead time.
    The main objectives of supply chain management are reducing costs, reducing inventory, and shortening delivery to improve customer service, thus enhancing the competitiveness of enterprises. In this study, it was researched the relationshop between lead time and order fulfillment cycle time, the order fulfillment and inventory turnover . After empirical exploration and discussion, the main findings are as follows:
    1. In the seller-oriented market, the way to purchase in advance will improve
    order fulfillment cycle time.
    2. Under the environment of customers’ uncertain prediction and weather risks,
    the way to increase “ safety stock” and “logistics control point” will improve
    order fulfillment rate.
    3. The way to use “increasing replenishment frequency”, “reducing production
    volume” and “central warehouse” will improve inventory turnover .
    Appears in Collections:[Graduate Institute & Department of Business Administration] Thesis

    Files in This Item:

    File SizeFormat
    index.html0KbHTML190View/Open

    All items in 機構典藏 are protected by copyright, with all rights reserved.


    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library & TKU Library IR teams. Copyright ©   - Feedback