English  |  正體中文  |  简体中文  |  Items with full text/Total items : 63993/96712 (66%)
Visitors : 3611607      Online Users : 356
RC Version 7.0 © Powered By DSPACE, MIT. Enhanced by NTU Library & TKU Library IR team.
Scope Tips:
  • please add "double quotation mark" for query phrases to get precise results
  • please goto advance search for comprehansive author search
  • Adv. Search
    HomeLoginUploadHelpAboutAdminister Goto mobile version
    Please use this identifier to cite or link to this item: https://tkuir.lib.tku.edu.tw/dspace/handle/987654321/69739


    Title: Development of an object-oriented scheduling model for construction projects
    Authors: Fan, Su-ling;Tserng, H. P;Wang, Ming-teh
    Contributors: 淡江大學土木工程學系
    Keywords: Scheduling;Soft logic;Object-oriented
    Date: 2003-05
    Issue Date: 2013-06-07 10:41:58 (UTC+8)
    Publisher: Amsterdam: Elsevier BV
    Abstract: 工程實務上有許多相同的作業項目在不同的施工區域不斷地重複,這類工程稱之為重複性工程。例如高樓建築、集合住宅、公路工程及管涵工程等。網圖技術已廣泛應用於各類型之工程進度排程,然而其應用於重複性工程卻有許多缺點。本研究旨在解決應用網圖技術於重複性工程之三個缺點:
    一、 網圖技術表達的複雜性:應用網圖技術表達重複性工程需要大量的作業項目,因此造成建立與更新進度時的困難度。
    二、 無法表達不固定作業關係(Soft Logic):網圖技術假定所有作業間關係皆為固定不變,然而工程實務上卻有許多作業間之關係是有各種不同排列組合的。
    三、 無法確保工班連續性(Work Continuity) :網圖技術僅考慮作業之前置後續關係,並未考量工班(資源)之連續性。
    本研究發展之模式包含以下三個模組:
    一、 輸入模組:依據工期、施工區域、.基本施作流程、施工區域之結構及作業關係將重複性工程分為2*2*2*2*2=32種類型,而後進一步發展可以表達各不同之重複性工程之界面,使排程者可輸入簡單之資料以表達重複性工程。
    二、 進度模組:探討影響不固定作業關係排程之影響因素與排序之經驗法則,而後發展表達不固定作業關係及影響其排序因素之界面並利用物件導向技術發展不固定作業關係排序演算法。
    三、 工班連續性模組:發展可確保工班連續性之演算法。
    Relation: Automation in Construction 12(3), pp.283-302
    DOI: 10.1016/S0926-5805(02)00092-4
    Appears in Collections:[Graduate Institute & Department of Civil Engineering] Journal Article

    Files in This Item:

    File SizeFormat
    index.html0KbHTML38View/Open

    All items in 機構典藏 are protected by copyright, with all rights reserved.


    DSpace Software Copyright © 2002-2004  MIT &  Hewlett-Packard  /   Enhanced by   NTU Library & TKU Library IR teams. Copyright ©   - Feedback